Construction Update – Michigan Tower 2 – August 2025
25th September 2025Core Poured to L33 with floor slabs completed to L28, and all panels now completed up to L19. The development now has the 1st fix partitions completed to L13 & 1st fix M&E complete to L08. Mist coat painting complete from L03 to L07 & flooring completed L03 to L06. Full kitchen fit out complete on L03.