Construction Update – Michigan Tower 2 – July 2025
4th September 2025Core is now poured to L32 with floor slabs (pour 1) complete to L26, slab (pour 2) currently ongoing. The external panels now complete to L16. All M&E Prefix complete to L12 & the 1st fix partitions complete to L9. 2nd fix partitions complete on L3 and 4 with the 2nd fix M&E now commenced on L3. Mist coat painting complete to L3 & all flooring commenced to L3.