Construction Update – The Tower – May 2018
2nd May 2018Staticus are progressing with zinc panel and glass installation to levels 13 and 14 and curtain walling grid installation to levels 14 through to 18, with all curtain walling grids in place on level 14. Roof works have progressed and insulation works completed.
Internally, first fix partitions are completed up to level 4 and levels 5 and 6 are underway. Kitchens and tiling are now completed to the show apartments and first fix M&E has been completed on level 2. Dry lining has commenced to levels 3,4 and sprinkler installation is now complete.