Construction Update – The Tower – June 2018
19th June 2018This month on site sees all curtain walling grids up to level 20 now been installed and aluminium has commenced on levels 1-4. Level 21 steelwork will commence this month. Curtain walling on levels 21 and above is not due to start until 30th July and we will be starting this on site on 18th June 6 weeks ahead of programme. First fix joinery is now complete on level 2. Tiling is now complete on levels 1 and 2 and kitchens are now complete on levels 1 -3. First fix joinery now complete on level 3 and underway on levels 4,5 and 6.
Back to blog