Construction Update – Michigan Tower 2 – March 2025

8th April 2025

Concrete frame to date is currently at level 14 with work on level 15 well underway.  Core is now ready for crane jump with ties connected at level’s 18/19.  All stairs installed up to level 19. Handover works for the concrete frame on level’s 2-10. Blockwork now progressing well on the ground level.