+44(0)151 236 8094

Construction Update – Michigan Tower 2 – June 2025

30th July 2025

The core is now poured to L30 with panels completed to L12 and progressing well.   Latex screed and M&E Prefix now completed up to L10.  The site has completed the 1st fix partitions from L02 to L07, and currently ongoing to L08 and L09.  The mist coat painting and flooring to commence soon.

Back to blog

Current projects

View all projects