Construction Update – Michigan Tower 2 – January 2025
13th February 2025Concrete Frame at Level 11 is currently underway with pour 2 completed, the sites level’s 18-19 core is now poured with stairs installed up to level 16 and drainage ongoing. Handover works for concrete frame on level’s 3-4 is continuing well. Staticus currently working on installing brackets on level 2.