Works to Tower 2 are underway and currently 5 days ahead of the contract completion date.  HE Simm M&E 1st fix are currently progressing well with the internal works, levels 1-6 handed over.  Intex have completed compartmentation and party walls on level 2, works now underway on level 3 to 5.