T3 Project is now in week 34.  The Excavation & construction of the 47 pile caps is now complete with the basement slab & columns progressing well, enabling the ground floor slab under the footprint of the tower to be constructed at the same time as areas of the basement floor slabs.  Tower crane is now installed to the full height required.