Construction Update – Media City – March 2017
31st May 2017Temporary power and lighting will continue to be installed on level 24-27 this month. The safety screens will come off and the hoist will be extended to level 27. Mechanical and Electrical work will continue with 1st fix on levels 11-22 with varying degrees of progress. Unitised cladding to continue on levels 7 -10 and we complete the unitised cladding on levels 2-4 as per approved sample.
Partitions and ceilings have commenced on level 5, restarting the internal production line with a new planned to start each week once handed over from the cladding subcontractor. 2nd fix internal finishing trades including joinery, kitchens, tiling and decorating will continue on levels 2- 4 with floor preparation and floor finishes starting. Lift installation in tower 1 has commenced from the basement up. LV Cable installation to T1 & T2 including construction of LV switch room for mains live.
We commence works to the main drainage connection early march with RVP’s being connected. The concrete frame is due for completion in March which also sees the topping out ceremony for the client. We aim to only work Monday – Friday 07:30 -18:00 and Saturday 07:30 – 13:00 and any out of hours works will only take place in exceptional circumstances.
Back to blog