Construction Update – Media City – February 2017
31st May 2017The concrete frame continues this month including the columns and slabs from level 23-26 with roof slab works underway as well. Temporary power and lighting will continue to be installed on levels 22-26. 2nd fix internal finishing trades including the kitchens and decorating will continue on levels 2- 4 with floor preparation and floor finishes starting at the end of February.
External envelope works will progress from level 5-8. Final aluminium cladding to the previously installed lower floors will commence next month. Partition and ceiling to start on level 5 once handed over from the cladding subcontractor which will restart the production line for internal finishes. Mechanical and Electrical work will continue with 1st fix on levels 9-20 with varying degrees of progress. Hoist to be extended to level 20.
We aim to work only Monday – Friday 07:30 -18:00 and Saturday 07:30 – 13:00 and any out of hours works will only take place in exceptional circumstances.