  • Inspections and commissioning are under way for sectional handovers this month.
  • Cladding of levels 26-27 and parapet installation is underway and to be complete within August.
  • Ground and 1st level curtain walling is also underway.
  • External landscaping has commenced around the East, North and South of tower 1.
  • The internal finishes are continuing from levels 18 – 26 at various stages.
  • Tower 2 concrete frame works are underway with double height columns being poured and the slipform being built on the ground level podium.