Construction Update – Manchester Waters October 2022
14th October 2022Block 3 is well under way with the external boarding now complete to level’s 1 & 2, including the frame work up to level 8. Internally, the partitions are ongoing on level’s 1 & 2 and intermisent paint completed to level 9.