Construction Update – Manchester Waters – February 2023

7th February 2023

Structural Steel is now complete with the Glazing & curtain walling ongoing to all elevations.  The Cladding installation is currently in progress to West elevation.  Internally, the pre fix M&E is ongoing upto level 12 & intumescent painting and core drilling ongoing to level 13.