Construction Update – Manchester Waters – August 2023

18th August 2023

Externally, the envelope works are now completed to East & West Elevations with hoist infill ongoing to South, the terrace roof installation is ongoing to level 13.  Internally, the final snagging & room lockdowns levels 1 to 10, final decoration on Levels 11 & 12.

 

 