Construction Update – Liverpool Waters – September 2024

11th October 2024

Core concrete works are completed with the temporary formwork currently being dismantled.  The Concrete frame slabs are poured up to level 27 and the Façade is progressing up to level 19.  Internal fit out works are now working to levels 2 – 13 with plaster complete to levels 2 & 3.