Construction Update – Liverpool Waters – April 2025

13th May 2025

Unitised curtain walling is now completed along with roof works.  The ground floor cladding is near completion.  All internal apartment fit out works continue to progress with floors 2-10 now at final snagging stage. All floors between 12-30 currently moving along well with the 1st fix M&E through to final fix.