+44(0)151 236 8094

Construction Update – Farnworth – May 2024

24th May 2024

The Farnworth project has seen the roof structures complete to both blocks C & D with roof coverings now well underway.   M&E & dry lining are progressing well through both blocks C&D.  Scaffold erection is nearing completion & brickwork to superstructure has commenced.  The timber frame structures of both blocks A&B have been completed.  Felt & batten is ongoing to ensure weathertight and ready for internal works.  Block E foundations have been poured and work is ongoing to the ground floor slab.

Back to blog

Current projects

View all projects