Construction Update – Farnworth – July 2024
31st July 2024Works are well under way with the roof tiling being largely complete to all areas and brickwork is currently progressing to all blocks. Power on has been achieved with lights on to Block D level 1 and final decoration progressing through. The landscaping has started in the shared access car park and will be progressing over the next coming weeks.