Construction Update – The Campus – August 2017
3rd August 2017We are currently progressing with the ground works to The Campus. The basement has been excavated, piles have been cropped and we are starting to install pile caps.
Over the coming weeks we will have deliveries of steel re-enforcement, concrete as well as some wagons to remove excavated material from site.
We have traffic management systems in place on the road, and a road sweeper on call to remove any spoil that may be tracked onto the road. No out of hours works are currently planned, although we may be open on a Saturday morning from time to time, to complete any critical activities that cannot be completed in the week.