Construction Update – The Tower – February 2018

26th February 2018

Electrical and mechanical riser have now been constructed up to level 12. The refuse chute has also been built up to level 12 and smoke vent up to level 10. Works have now commenced on the show apartments on floor level 1. Apartments 8 and 9 external and party walls have been boarded along with the install of the ceiling grid. First fix ductwork is now up to level 13 whilst sprinkler installation is up on floor level 12. Primary distribution of steel wired armoured cable feed to apartments as well as water main have commenced installation and lighting/data points connections have started to be picked up within the general landlord areas such as the lift lobby core. For the façade; brackets have been fully fixed to the mullions on Level 1 as well as installation of glazing and aluminium cassettes, these works are currently continuing up the tower on levels 2,3 and 4.