Construction Update- Media City T3 – March 2022
8th March 2022The in-situ concrete frame is currently progressing in good time with the ground floor slab nearing completion, which will then enclose this phase of the basement. The construction of the core, consisting of stairs, lobbies and lift shafts are up to level 14 and the concrete floor slabs are complete up to level 6.