Construction Update – Media City – April 2017

Expanded are to finish the concrete snagging and are demobilising from site this month.  Vermont have taken ownership of the crane with an Expanded crane team working for Vermont until 08/05/2017.

Hoists are to be extended to level 27 and mechanical and electrical work will continue with 1st fix on levels 19-26  with varying degrees of progress.  Unitised cladding to continue on levels 12 -15.  Partition and ceiling works to continue on level 7 to 11 with follow on trades of 1st fix M&E, joinery, mist coating, bathrooms, kitchens and floor laying preparation.  2nd fix internal finishing trades including joinery, kitchens and decorating will continue on levels 4-6 and floor finishes will follow.

Snagging and cleaning is to continue on levels 2-5. and lift installation in tower 1 continues from the basement up.  Parapet steelwork and roofing works are to commence on level 27 and the steel work for the 1st level deck is to continue on the East elevation.  Drainage connections and mains water works to commence this month along with a BT diversion for telecoms and data.

We aim to only work Monday – Friday 07:30 -18:00 and Saturday 07:30 – 13:00 and any out of hours works will only take place in exceptional circumstances.